Hi There,
We have a question about how to pull the Open PO from ECC to EWM and convert it to EGR.
in SAP help, it suggest to schedule report /SCWM/ERP_DLV_DELETE in EWM, but when I run this report in EWM, it can't find my open POs. But when I run ERP report /SPE/INB_EGR_CREATE, it can find my open PO, and able to transfer it to EWM.
My question is:
1. What's difference for these 2 approaches to create the EGRs in EWM? Why SAP suggest use EWM one, and indicate only use ERP one in exceptional circumstances?
2. I prefer the the ECC one, as it provide more selection criteria, like confirmation control key.material etc.
any idea?
Thank you very much for your help.
++++++++++++++++++++++++++++++++++++
Integration
You usually schedule report /SCWM/ERP_DLV_DELETE so that Extended Warehouse Management (EWM) requests new expected goods receipts from SAP ERP.You use these expected goods receipts as templates to generate an inbound delivery in EWM manually.
In exceptional circumstances, you can also use report /SPE/INB_EGR_CREATE in SAP ERP to generate an expected goods receipt.SAP ERP informs EWM about this, and EWM generates an expected goods receipt as well.