Hi Gurus,
Good day!
We have a scenario wherein Delivery Completed Indicator needs to be automatically ticked once delivery is already PGI. However there are cases wherein this field in the PO is not ticked automatically and so far the difference we found between the correct and incorrect is that the incorrect one the delivery qty is zero. ECC passed delivery to EWM having quantity = 10 and EWM updated this delivery quantity to zero. Once this delivery passed to ECC it is expected that the delivery quantity reflected is ZERO and the Business expects that PO Delivery Completed Indicator must be ticked automatically and our issue is that this Delivery Completed Indicator in PO is not automatically ticked.
Please enlighten me where can I find possible programs that was triggered since so far during my debug I was not able to capture the program responsible for this. I read some articles but not helping. Or are there configurations needed to be cheked or updated for this scenario?
I really appreciate your help on this.
Thank you.
Regards,
Rish