Scenario is as follow.
Vendor will send goods in a HU of 100 pcs. subsequently goods will be moved to oiling workcenter for oiling. finally the goods are moved to packing work center where each pc's is packed into one HU and these 100 HU's will be placed into final bin.
I configured in the system with the steps unload oiling , packing ( oiling and packing at different work centers) and putaway.
my pack spec is one product is packed into one HU.
system is not me to repack at packing work center as the final waiting task exist in the system.
any clue how to achieve this?